Enhanced process and product understanding are the basic tenets of Quality by Design (QbD). Although significant advances have been made, appropriate characterization and management of raw materials remain a concern for the regulatory authorities. Because of the large number of raw materials that typically are used in biotech processes, a QbD-based approach for raw material management must be based on scientific knowledge and risk analysis. This strategy will ensure that adequate characterization is performed on those raw materials that have the most effect on process consistency and product quality. Part 1 of this article presented an approach for raw material management following QbD principles. In Part 2, we discuss how to conduct risk assessments for biotech raw materials, along with examples of risk assessment tools that can be used.


Anurag S. Rathore
The contribution of raw materials to product quality, safety and process performance is considerable, in part because of the potential to introduce contaminants. It is therefore important in designing processes and selecting raw materials that careful thought be given to understanding their purpose and suitability for the intended use. Raw materials also are a major source of variability, and steps must be taken to minimize any negative effects arising from materials and their sources. There essentially are two parts to this: prevention through assessment, inspection and control of incoming materials; and intervention, in which processing conditions are modified to account for variability, sometimes through continued monitoring of materials and their effect on process performance.

Part 2 of this 20th article in the Elements of Biopharmaceutical Production series discusses how to conduct risk assessments, handling risk communication to stakeholders, and give examples of applying risk assessment tools for analyzing raw materials in biotech processes.

TOOLS FOR RISK ASSESSMENT, EVALUATION, AND COMMUNICATION

Assessment


SAFC
There are a number of different risk assessment tools available in a range of detail and complexity, and it is important to use a methodology suited to the purpose of the assessment. The approach begins with identification of risk factors through brainstorming, in which ideas are recorded with minimal critical appraisal; or Fishbone or Ishikawa diagrams, which offer a more structured approach. These can be used either to map the process generally, working backwards from the endpoint and identifying all possible risks at a given point, or to structure the evaluation around a given sent of questions at each point (e.g., the 6M's: material, method, measurement, machine, man, and mother nature).1,2 After they are identified, risks can be analyzed by a variety of tools, such as preliminary hazard analysis (PHA), failure mode effects analysis (FMEA), failure mode effects criticality analysis (FMECA), What-if?, fault tree analysis (FTA), event tree analysis, cause consequence analysis, hazard and operability analysis (HAZOP), and hazard analysis and critical control points (HACCP).


Table 1. Comparison of different risk assessment tools
A comparison of some risk assessment tools is given in Table 1. PHA scores risk based on severity and occurrence on a five-point scale, with the highest scores representing the greatest risk. FMEA adds detection to the scoring system. By adding the extra scoring category, it is relatively simple to advance a PHA assessment to FMEA, which may become appropriate as more information is known. Additional criteria may be added to distinguish between risks to more or fewer critical quality attributes (CQAs), bringing it to a FMECA assessment. HAZOP assessments commonly are used to evaluate risk to operators or environmental risks.

Evaluation

The next stage of the risk assessment is risk evaluation, in which the calculated risk index rating is compared to established criteria to determine high-risk items and whether additional information is required, and what mitigation activities are required to bring risk to an acceptable level.

Communication

Finally, communication is an important part of any risk management plan. It is essential that the outcome of the risk assessment is communicated to stakeholders and management and the recommendations for further mitigation or acceptance of residual risk are taken at the appropriate level.


blog comments powered by Disqus

ADVERTISEMENT

ADVERTISEMENT

Bristol-Myers Squibb Announces Agreement to Acquire HER2-Targeted Cancer Treatment
October 29, 2014
Amgen, Sanofi, and Ono Pharmaceuticals Partner with Universities on Transmembrane Protein Research
October 28, 2014
Yale and Gilead Extend Sequencing Initiative
October 28, 2014
Contract Research and Manufacturing Organization Paragon Bioservices Raises $13 Million
October 28, 2014
Novartis Sells Influenza Vaccine Business to CSL for $275 Million
October 27, 2014
Author Guidelines
Source: BioPharm International,
Click here